Excavation
Excavation in hard rock with breaker
6 variants
Excavation in hard rock, breaker, 1.5 to 3 m deep — cart away to tipAED 205 / m³Excavation in hard rock, breaker, 1.5 to 3 m deep — stockpile on siteAED 133 / m³Excavation in hard rock, breaker, 3 to 6 m deep — cart away to tipAED 251 / m³Excavation in hard rock, breaker, over 6 m deep — cart away to tipAED 324 / m³Excavation in hard rock, breaker, up to 1.5 m deep — cart away to tipAED 168 / m³Excavation in hard rock, breaker, up to 1.5 m deep — stockpile on siteAED 108 / m³